COMPLETED PROJECTS

  • PROJECT NAME LOCATION TOTAL COST DATE STARTED TARGET DATE OF COMPLETION STATUS
    PROPOSED CHRISTMAS TREE AND BELEN


    BUENAVISTA WATER DISTRICT, BRGY 3, BUENAVISTA, AGUSAN DEL NORTE


    P 20,000.00


    November 22, 2018


    November 30, 2018


    Accomplished last Nov. 30, 2018


    PUMP STATION NO. 5 EMBANKMENT


    PUMP STA. #5, BRGY RIZAL, BUENAVISTA, AGUSAN DEL NORTE


    P 100,000.00


    October 8, 2018


    October 23, 2018


    Accomplished last Oct. 21, 2018


    PROPOSED CONCRETE PAD MOUNTED FOR PUMP STATION NO.3's TRANSFORMERS


    PUMP STA. #3, BRGY MALPOC, BUENAVISTA, AGUSAN DEL NORTE


    P 100,000.00


    October 8, 2018


    October 23, 2018


    Accomplished last Oct. 23, 2018


    PROPOSED CARPORT STEEL ROOFING


    BUENAVISTA WATER DISTRICT, BRGY 3, BUENAVISTA, AGUSAN DEL NORTE


    P 50,000.00


    October 20, 2018


    November 11, 2018


    Accomplished last Nov. 11, 2018


    Proposed Cashier's Office Renovation

    BUENAVISTA WATER DISTRICT, BRGY 3, BUENAVISTA, AGUSAN DEL NORTE

    P 120,000.00

    September 22, 2018

    October 10, 2018

    Accomplished last Oct. 6, 2018

  • PROJECT NAME LOCATION TOTAL COST DATE STARTED TARGET DATE OF COMPLETION STATUS
    BARANGAY ABILAN PIPELINE EXTENSION (Phase I) Barangay Abilan, Buenavista, Agusan del Norte P 1,250,000.00

    January 25, 2017


    April 24, 2017


    Completed last February 22, 2017


    RENOVATION OF ANNEX BUILDING


    BWD Office, Rizal Ave., Barangay 3, Buenavista, Agusan del Norte


    P 55,855.00


    January 12, 2017


    January 31, 2017


    Completed last January 30, 2017


    PROPOSED BWD I.T. OFFICE GLASS WALL AND WINDOWS


    Buenavista Water District's Office, Rizal Avenue, Barangay 3, Buenavista, Agusan del Norte


    P 40,000.00


    July 31, 2017


    August 4, 2017


    Project completed last August 3, 2017


    PROPOSED DRILLING FOR EXPLORATORY AND PRODUCTION DEEP WELL


    Barangay Rizal, Buenavista, Agusan del Norte


    P 1,571,475.92


    January 12, 2017


    April 11, 2017


    Project completed last May 27, 2017


    TRANSMISSION LINE FROM PUMP STATION NO. 5 TO PUMP STATION NO. 4


    BRGY RIZAL, BUENAVISTA, AGUSAN DEL NORTE


    P 630,000.00


    December 4, 2017


    December 29, 2017


    Project completed last December 14, 2017


    So. TABIGUE PIPELINE EXTENSIONC(PHASE 2)


    So. TABIGUE, BARANGAY SACOL, BUENAVISTA, AGUSAN DEL NORTE


    P 130,000.00


    November 3, 2017


    December 29, 2017


    Project completed last December 20, 2017


    CALAYAGON PIPELINE EXTENSION


    So. CALAYAGON, BARANGAY MALPOC, BUENAVISTA, AGUSAN DEL NORTE


    P 450,000.00


    November 3, 2017


    December 29, 2017


    Project completed last December 6, 2017


    BARANGAY ABILAN PIPELINE EXTENSION (PHASE 2)


    So. SAN JUAN, BARANGAY ABILAN, BUENAVISTA, AGUSAN DEL NORTE


    P 170,000.00


    November 3, 2017


    December 29, 2017


    Project completed last Nov. 15, 2017


    PUROK 4-A, BARANGAY MANAPA PIPELINE EXTENSION
    Purok 4-A, BARANGAY MANAPA, BUENAVISTA, AGUSAN DEL NORTE


    P 200,000.00


    November 3, 2017


    December 29, 2017


    Project completed last Nov. 15, 2017


    SUPPLY AND INSTALLATION OF A 6 INCHES DIAMETER DISCHARGE LINES

    BRGY RIZAL, BUENAVISTA, AGUSAN DEL NORTE


    P 500,000.00


    December 1, 2017


    December 31, 2017


    Accomplished last Mar. 27, 2018, no payment made yet.


    PROPOSED PUMP HOUSE NUMBER 5


    BRGY RIZAL, BUENAVISTA, AGUSAN DEL NORTE


    P 540,000.00


    November 13, 2017


    February 28, 2018


    Accomplished last Mar. 2, 2018


    PROPOSED PERIMETER FENCE FOR PUMP STATION NO.5


    BRGY RIZAL, BUENAVISTA, AGUSAN DEL NORTE


    P 720,000.00


    November 13, 2017


    February 28, 2018


    Accomplished last Jan. 25, 2018


    SUPPLY AND INSTALLATION OF A 6 INCHES DIAMETER DISCHARGE LINES


    BRGY RIZAL, BUENAVISTA, AGUSAN DEL NORTE


    P 500,000.00


    December 1, 2017


    December 31, 2017


    Accomplished last Mar. 27, 2018


    Power allocation with appurtenances and purchase of one (1) set 30 hp submersible pump/motor with complete accessories for Pumpstation No. 5 A.)Delivery,Installation,Supervision & Start-up Commissioning of Transformer complete w/ accessories B.)Delivery,Installation,Supervision,& Start-up Commissioning of one (1) unit Brandnew Submersible pump with controller set complete w/ accessories BRGY RIZAL, BUENAVISTA, AGUSAN DEL NORTE


    P 978,000.00


    A.) December 1, 2017 B.) December 6, 2017


    A.) January 8, 2018 B.) January 6, 2018


    Accomplished last June 21, 2018


  • PROJECT NAME LOCATION TOTAL COST DATE STARTED TARGET DATE OF COMPLETION STATUS
    BARANGAY MANAPA TO So.DUMUROG PIPE LOOPING (phase 1) So. Dumurog, Barangay Matabao, Buenavista, Agusan del Norte P 220,000.00
    March 1, 2016
    April 7, 2016
    Completed last March 18, 2016
    NATIONAL HIGHWAY PIPE;INE EXTENSION (Buenavista - Nasipit Boundary)
    National Highway, Buenavista - Nasipit Boundary, Agusan del Norte
    P 155,000.00
    February 16, 2016
    March 4, 2016
    Completed last February 29, 2016
    BWD PERIMETER WALL REPAINTING, GM'S OFFICE RENOVATION, AND STOCK ROOM'S ROOF AND PURLINS REPAIR
    Brgy 3, Buenavista, Agusan del Norte
    P 100,000.00
    January 7, 2016
    January 24, 2016
    Completed last January 19, 2016
    RENOVATION OF BWD CUSTOMER'S COMFORT ROOMS (MALE & FEMALE)
    BWD Office, Rizal Ave., Barangay 3, Buenavista, Agusan del Norte
    P 160,000.00
    May 19, 2016
    June 30, 2016
    Completed last June 28, 2016
    MARCONVILLE SUBDIVISION PIPELINE EXPANSION (PHASE II)
    Marconville Subdivsion, Brgy Matabao, Buenavista, Agusan del Norte
    P 140,000.00
    May 18, 2016
    June 17, 2016
    Completed last May 31, 2016
    Brgy. Guinabsan Pipeline Extension
    Brgy Guinabsan, Buenavista, Agusan del Norte
    P 810,000.00
    July 4, 2016
    September 21, 2016
    Completed last September 19, 2016
    BWD Customer's Lounge Renovation
    Brgy 3, Buenavista, Agusan del Norte
    P 120,000.00
    July 14, 2016
    August 8, 2016
    Completed last August 1, 2016
  • PROJECT NAME LOCATION DATE STARTED TARGET DATE OF COMPLETION STATUS
    Repair Pump House No. 3 Brgy. Malpoc, Bta., ADN May 6, 2015 May 13, 2015 100% completed
    Transmission Line from Pump Station No. 3 to Pump Station No. 2 (Phase II) Brgy. Malpoc, Bta., ADN May 20, 2015 June 19, 2015 100% completed
    Pump Station No. 2 Bypass Outlet Brgy. Malpoc, Bta., ADN June 23, 2015 July 10, 2015 100% completed
    Malapong Pipeline Extension Brgy. Malapong, Bta., ADN July 14, 2015 September 30, 2015 100% completed
    Macalang Pipeline Extension Brgy. Macalang, Bta., ADN August 10, 2015 September 30, 2015 100% completed
  • PROJECT NAME LOCATION DATE STARTED TARGET DATE OF COMPLETION STATUS
    Jamboree Pipeline Extension Jamboree, National Highway, Bta., ADN February 14, 2014 March 31, 2015 100% completed
    Marconville Subdivision Pipeline Expansion Brgy. Matabao, Bta., ADN November 21, 2013 August 8, 2014 100% completed
    Construction of Pump House No. 4 Brgy. Rizal, Bta., ADN December 16, 2013 August 15, 2014 100% completed
    Installation of Electro-mechanical equipments for Pump Station No. 4 P4 Brgy. Rizal, Bta., ADN December 13, 2013 July 18, 2014 100% completed
    Public Market - Brgy. 3 Pipe Looping Brgy. 3, Bta., ADN August 20, 2014 September 2, 2014 100% completed
    Jamboree-Brgy. Alubihid Pipeline Extension (Phase I) National Highway, Bta., ADN August 26, 2014 October 14, 2014 100% completed
    Pipes Storage Building Brgy. Malpoc, Bta., ADN October 8, 2014 October 28, 2014 100% completed
    Restoration of Damaged Concrete Pavement Due to Excavation for Pipe Laying Brgy. Malpoc, Bta., ADN October 21, 2014 October 28, 2014 100% completed
    Transmission Lines from Pump Station No. 3 to Pump Station No. 2 (Phase I) Brgy. Malpoc, Bta., ADN November 12, 2014 Nov. 28, 2014 100% completed
    Reservoir Perimeter Fence Brgy. Malpoc, Bta., ADN December 4, 2014 December 12, 2014 100% completed
  • PROJECT NAME LOCATION DATE STARTED TARGET DATE OF COMPLETION STATUS
    Tabigue Pipeline Expansion (915 m) Sitio Tabigue Brgy. Sacol July 16, 2013 July 31, 2013 100% completed
    Os-os Pipeline Expansion (365 m) Sitio Os-os Brgy. 1. July 16, 2013 August 12, 2013 100% completed
    P1-Manapa Pipeline Expansion (386 m) P1 Brgy. Manapa August 1, 2013 August 16, 2013 100% completed
    P4-Manapa Pipeline Expansion (226 m) P4 Brgy. Manapa August 7, 2013 August 15, 2013 100% completed
    Manapa Pipeline Expansion (1,300 m) Sabang, Manapa November 13, 2013 November 22, 2013 100% completed