Projects

Completed Projects from 2013 - 2019

C.Y. 2019

Project NameLocationTotal CostDate StartedNo. of ExtensionsTarget Completion DateStatusBeneficiaris
Pump Station No. 3 Primary Busbar Metering with AccessoriesMalpoc, Buenavista, ADNP 500,000.00December 5, 2018noneJanuary 5, 2019> Accomplished last March 8, 2019
> Paid last April 30, 2019
All Buenavista Water District Concessionaires
Proposed Pump Station No. 3 Building RepairMalpoc, Buenavista, ADNP 100,000.00January 15, 2019noneFebruary 22, 2019> Accomplished last Feb. 20, 2019
> Date Purchase of Materials: December 11, 2018
Buenavista Water District employees and for the building to be resilient
Transmission Line from Pump Station No. 5 to Brgy. 1 (National Highway)Rizal - National HighwayP 7,739,900.00February 1, 2019noneDecember 31, 2019> Accomplished last Dec. 27, 2019
> Date Purchase of Materials: Septenber 20, 2018
All Buenavista Water District Concessionaires
Parallel Transmission Lines (Phase 1)National Highway, Buenavista, Agusan del NorteP 1,499,160.00 (Tax Provision 2018)June 1, 2019noneSeptember 30, 2019> The project has not yet started becasuse the projects pipeline will be tap at the last pipe of the transmission line project
> Materials are already paid
> Date purchased of materials: October 5, 2018
> The project's implementing date is moved from January 1, 2020 to March 31, 2020 due to the new location of distribution pipeline of the Transmission line project
All Buenavista Water District concessionaires
Parallel Transmission Lines (Phase 2)National Highway, Buenavista, Agusan del NorteP 1,500,000.00 (Tax Provision 2019)April 2020noneJune 30, 2020> The project has not yet started becuase the project's pipeline will be tap at the last pipe of the parallel transmission line project (phase 1).
> Date purchased of pipes materials: November 18, 2019
> Partial delivery of CI fittings and no payment has been made yet
All Buenavista Water District concessionaires
Additional length for the transmission line projectMalpoc - National HighwayP 970,000.00November 11, 2019noneDecember 31, 2019> Accomplished last December 6, 2019
> Materials only
> Date of purchased of pipes: October 18, 2019
All Buenavista Water District concessionaires
Proposed building repair and construction of structures for the Buenavista Water District's 5 Pump StationsBrgy. Malpoc and Rizal, Buenavista, Agusan del NorteP 897,485.73November 14, 2019noneFebruary 2, 2020> On-going
> Awarded to J-R3 Construction and Supply
> Winning Bid Amount: P 866,970.00
Proposed Drilling for exploratory and production deep wellBrgy. Rizal, Buenavista, Agusan del NorteP 1,540,973.21December 18, 2019noneApril 15, 2020> Awarded to KGD Builders
> Bid Amount: 1,501,449
> No payment have been made yet since the contractor has not yet mobilized/has not yet started their drilling activities.
> Purchase order dated October 18, 2019

C.Y. 2018

PROJECT NAMELOCATIONTOTAL COSTDATE STARTEDTARGET DATE OF COMPLETIONSTATUS
PROPOSED CHRISTMAS TREE AND BELEN


BUENAVISTA WATER DISTRICT, BRGY 3, BUENAVISTA, AGUSAN DEL NORTE


P 20,000.00


November 22, 2018


November 30, 2018


Accomplished last Nov. 30, 2018


PUMP STATION NO. 5 EMBANKMENT


PUMP STA. #5, BRGY RIZAL, BUENAVISTA, AGUSAN DEL NORTE


P 100,000.00


October 8, 2018


October 23, 2018


Accomplished last Oct. 21, 2018


PROPOSED CONCRETE PAD MOUNTED FOR PUMP STATION NO.3's TRANSFORMERS


PUMP STA. #3, BRGY MALPOC, BUENAVISTA, AGUSAN DEL NORTE


P 100,000.00


October 8, 2018


October 23, 2018


Accomplished last Oct. 23, 2018


PROPOSED CARPORT STEEL ROOFING


BUENAVISTA WATER DISTRICT, BRGY 3, BUENAVISTA, AGUSAN DEL NORTE


P 50,000.00


October 20, 2018


November 11, 2018


Accomplished last Nov. 11, 2018


Proposed Cashier's Office Renovation

BUENAVISTA WATER DISTRICT, BRGY 3, BUENAVISTA, AGUSAN DEL NORTE

P 120,000.00

September 22, 2018

October 10, 2018

Accomplished last Oct. 6, 2018

C.Y. 2017

PROJECT NAMELOCATIONTOTAL COSTDATE STARTEDTARGET DATE OF COMPLETIONSTATUS
BARANGAY ABILAN PIPELINE EXTENSION (Phase I) Barangay Abilan, Buenavista, Agusan del Norte P 1,250,000.00

January 25, 2017


April 24, 2017


Completed last February 22, 2017


RENOVATION OF ANNEX BUILDING


BWD Office, Rizal Ave., Barangay 3, Buenavista, Agusan del Norte


P 55,855.00


January 12, 2017


January 31, 2017


Completed last January 30, 2017


PROPOSED BWD I.T. OFFICE GLASS WALL AND WINDOWS


Buenavista Water District's Office, Rizal Avenue, Barangay 3, Buenavista, Agusan del Norte


P 40,000.00


July 31, 2017


August 4, 2017


Project completed last August 3, 2017


PROPOSED DRILLING FOR EXPLORATORY AND PRODUCTION DEEP WELL


Barangay Rizal, Buenavista, Agusan del Norte


P 1,571,475.92


January 12, 2017


April 11, 2017


Project completed last May 27, 2017


TRANSMISSION LINE FROM PUMP STATION NO. 5 TO PUMP STATION NO. 4


BRGY RIZAL, BUENAVISTA, AGUSAN DEL NORTE


P 630,000.00


December 4, 2017


December 29, 2017


Project completed last December 14, 2017


So. TABIGUE PIPELINE EXTENSIONC(PHASE 2)


So. TABIGUE, BARANGAY SACOL, BUENAVISTA, AGUSAN DEL NORTE


P 130,000.00


November 3, 2017


December 29, 2017


Project completed last December 20, 2017


CALAYAGON PIPELINE EXTENSION


So. CALAYAGON, BARANGAY MALPOC, BUENAVISTA, AGUSAN DEL NORTE


P 450,000.00


November 3, 2017


December 29, 2017


Project completed last December 6, 2017


BARANGAY ABILAN PIPELINE EXTENSION (PHASE 2)


So. SAN JUAN, BARANGAY ABILAN, BUENAVISTA, AGUSAN DEL NORTE


P 170,000.00


November 3, 2017


December 29, 2017


Project completed last Nov. 15, 2017


PUROK 4-A, BARANGAY MANAPA PIPELINE EXTENSION
Purok 4-A, BARANGAY MANAPA, BUENAVISTA, AGUSAN DEL NORTE


P 200,000.00


November 3, 2017


December 29, 2017


Project completed last Nov. 15, 2017


SUPPLY AND INSTALLATION OF A 6 INCHES DIAMETER DISCHARGE LINES

BRGY RIZAL, BUENAVISTA, AGUSAN DEL NORTE


P 500,000.00


December 1, 2017


December 31, 2017


Accomplished last Mar. 27, 2018, no payment made yet.


PROPOSED PUMP HOUSE NUMBER 5


BRGY RIZAL, BUENAVISTA, AGUSAN DEL NORTE


P 540,000.00


November 13, 2017


February 28, 2018


Accomplished last Mar. 2, 2018


PROPOSED PERIMETER FENCE FOR PUMP STATION NO.5


BRGY RIZAL, BUENAVISTA, AGUSAN DEL NORTE


P 720,000.00


November 13, 2017


February 28, 2018


Accomplished last Jan. 25, 2018


SUPPLY AND INSTALLATION OF A 6 INCHES DIAMETER DISCHARGE LINES


BRGY RIZAL, BUENAVISTA, AGUSAN DEL NORTE


P 500,000.00


December 1, 2017


December 31, 2017


Accomplished last Mar. 27, 2018


Power allocation with appurtenances and purchase of one (1) set 30 hp submersible pump/motor with complete accessories for Pumpstation No. 5 A.)Delivery,Installation,Supervision & Start-up Commissioning of Transformer complete w/ accessories B.)Delivery,Installation,Supervision,& Start-up Commissioning of one (1) unit Brandnew Submersible pump with controller set complete w/ accessories BRGY RIZAL, BUENAVISTA, AGUSAN DEL NORTE


P 978,000.00


A.) December 1, 2017 B.) December 6, 2017


A.) January 8, 2018 B.) January 6, 2018


Accomplished last June 21, 2018


C.Y. 2016

PROJECT NAMELOCATIONTOTAL COSTDATE STARTEDTARGET DATE OF COMPLETIONSTATUS
BARANGAY MANAPA TO So.DUMUROG PIPE LOOPING (phase 1) So. Dumurog, Barangay Matabao, Buenavista, Agusan del Norte P 220,000.00
March 1, 2016
April 7, 2016
Completed last March 18, 2016
NATIONAL HIGHWAY PIPE;INE EXTENSION (Buenavista - Nasipit Boundary)
National Highway, Buenavista - Nasipit Boundary, Agusan del Norte
P 155,000.00
February 16, 2016
March 4, 2016
Completed last February 29, 2016
BWD PERIMETER WALL REPAINTING, GM'S OFFICE RENOVATION, AND STOCK ROOM'S ROOF AND PURLINS REPAIR
Brgy 3, Buenavista, Agusan del Norte
P 100,000.00
January 7, 2016
January 24, 2016
Completed last January 19, 2016
RENOVATION OF BWD CUSTOMER'S COMFORT ROOMS (MALE & FEMALE)
BWD Office, Rizal Ave., Barangay 3, Buenavista, Agusan del Norte
P 160,000.00
May 19, 2016
June 30, 2016
Completed last June 28, 2016
MARCONVILLE SUBDIVISION PIPELINE EXPANSION (PHASE II)
Marconville Subdivsion, Brgy Matabao, Buenavista, Agusan del Norte
P 140,000.00
May 18, 2016
June 17, 2016
Completed last May 31, 2016
Brgy. Guinabsan Pipeline Extension
Brgy Guinabsan, Buenavista, Agusan del Norte
P 810,000.00
July 4, 2016
September 21, 2016
Completed last September 19, 2016
BWD Customer's Lounge Renovation
Brgy 3, Buenavista, Agusan del Norte
P 120,000.00
July 14, 2016
August 8, 2016
Completed last August 1, 2016

C.Y. 2015

PROJECT NAMELOCATIONDATE STARTEDTARGET DATE OF COMPLETIONSTATUS
Repair Pump House No. 3Brgy. Malpoc, Bta., ADNMay 6, 2015May 13, 2015 100% completed
Transmission Line from Pump Station No. 3 to Pump Station No. 2 (Phase II)Brgy. Malpoc, Bta., ADNMay 20, 2015June 19, 2015 100% completed
Pump Station No. 2 Bypass OutletBrgy. Malpoc, Bta., ADNJune 23, 2015July 10, 2015 100% completed
Malapong Pipeline ExtensionBrgy. Malapong, Bta., ADNJuly 14, 2015September 30, 2015 100% completed
Macalang Pipeline ExtensionBrgy. Macalang, Bta., ADNAugust 10, 2015September 30, 2015 100% completed

C.Y. 2014

PROJECT NAMELOCATIONDATE STARTEDTARGET DATE OF COMPLETIONSTATUS
Jamboree Pipeline ExtensionJamboree, National Highway, Bta., ADNFebruary 14, 2014March 31, 2015 100% completed
Marconville Subdivision Pipeline ExpansionBrgy. Matabao, Bta., ADNNovember 21, 2013August 8, 2014 100% completed
Construction of Pump House No. 4Brgy. Rizal, Bta., ADNDecember 16, 2013August 15, 2014 100% completed
Installation of Electro-mechanical equipments for Pump Station No. 4P4 Brgy. Rizal, Bta., ADNDecember 13, 2013July 18, 2014 100% completed
Public Market - Brgy. 3 Pipe LoopingBrgy. 3, Bta., ADNAugust 20, 2014September 2, 2014 100% completed
Jamboree-Brgy. Alubihid Pipeline Extension (Phase I)National Highway, Bta., ADNAugust 26, 2014October 14, 2014100% completed
Pipes Storage Building Brgy. Malpoc, Bta., ADN October 8, 2014October 28, 2014100% completed
Restoration of Damaged Concrete Pavement Due to Excavation for Pipe LayingBrgy. Malpoc, Bta., ADNOctober 21, 2014October 28, 2014100% completed
Transmission Lines from Pump Station No. 3 to Pump Station No. 2 (Phase I)Brgy. Malpoc, Bta., ADNNovember 12, 2014Nov. 28, 2014100% completed
Reservoir Perimeter Fence Brgy. Malpoc, Bta., ADNDecember 4, 2014December 12, 2014100% completed

C.Y. 2013

PROJECT NAMELOCATIONDATE STARTEDTARGET DATE OF COMPLETIONSTATUS
Tabigue Pipeline Expansion (915 m)Sitio Tabigue Brgy. SacolJuly 16, 2013July 31, 2013 100% completed
Os-os Pipeline Expansion (365 m) Sitio Os-os Brgy. 1.July 16, 2013 August 12, 2013 100% completed
P1-Manapa Pipeline Expansion (386 m) P1 Brgy. Manapa August 1, 2013August 16, 2013 100% completed
P4-Manapa Pipeline Expansion (226 m) P4 Brgy. Manapa August 7, 2013August 15, 2013 100% completed
Manapa Pipeline Expansion (1,300 m) Sabang, ManapaNovember 13, 2013November 22, 2013 100% completed